Start with the payment basis

The payment mechanism and the delivery model answer different questions. One explains how work is valued; the other allocates design and delivery responsibilities.

Lump sum

An agreed price covers a defined scope, subject to the contract’s adjustments. It generally needs a sufficiently clear design and specification.

Remeasurement

Payment is based on measured quantities and agreed rates. Quantity changes can affect the final amount.

Cost-plus

The employer reimburses allowable costs and an agreed fee. Cost definitions, supporting records and expenditure controls need particular attention.

Target cost

A target is agreed, with savings or overruns allocated under the contract’s sharing rules. The target is not automatically a fixed-price guarantee.

Questions to take into your project

Before choosing: assess design maturity, quantity uncertainty, risk allocation and the team’s capacity to manage records.